Bids List for Capital Improvement Projects

Image Click a project ID number to load the project web page. The project page contains links to bid results, invitation for bids, and the construction plans.
Date BidStatusProjIDTitleDescription
05/21/2019Image
Proposed
02042Llano Trunk Lining - W College Utilities FacilityThis project will rehabilitate approximately 1,100 feet of pipeline by cured-in-place pipe (CIPP) lining inserted into the existing sewer main pipe, located within the W. College Utilities Facility. Six manholes will be rehabilitated a corrosion resistant epoxy liner for protection against future hydrogen sulfide deterioration.
05/21/2019Image
Proposed
02252Pavement Preventive Maintenance 2019This project will consist of performing preventive maintenance on City streets by contract. Work to be completed is crack sealing, asphalt dig outs, and pavement resurfacing
05/15/2019Image
Proposed
021862019 Pavement MarkingThis project is for the annual contract maintenance installation of edge lines, raised pavement markers, and bike lane lines throughout Santa Rosa. It is intended to ensure bicyclists remain within a bike pathway on the street system by highlighting travel lanes and bike lanes and to provide striping modifications to the street system as needed.
05/08/2019Image
Proposed
02260Removal of Fire-Damaged Hazardous TreesPublic scope is missing from database.
05/02/2019Image
Proposed
01909Northerly Slope Protection Ponds C & D and Pond B Slope RepairThe northerly slopes of reclaimed water Ponds C and D need protection from further erosion created by wave action from storm events. In addition, the westerly slope of Pond B suffered a slope failure during the winter of 2018-2019 and needs repair.
05/01/2019Image
Proposed
02113Roseland Pavement MaintenanceTo share in the City's transportation infrastructure costs for the Roseland annexation, the County will provide funding of $6.62M over a 10-year period (Transportation Payment") to cover pavement improvement costs in the Roseland annexation area which may include asphalt paved walkways on the shoulders and required ADA upgrades.
04/30/2019Image
Proposed
01568Grosse Ave, El Camino Way, and Augustan Ave Sewer and Water Replacement - Dowling Ct to East Haven DrThis project will replace sewer and water mains in Augustan Avenue, El Camino Way from Grosse Avenue to Augustan Avenue, and in Grosse Avenue from El Camino Way to Dowling Court. This project will abandon an inaccessible backyard easement and re-plumb the tributary lots to the public sewer in the street. Ten pedestrian ramps will be replaced. All streets will be reconstructed.
04/29/2019Image
Proposed
02003Donahue, Decker, Boyce & Petaluma Hill Sewer and Water Main ImprovementsThis project will remove and replace approximately 500 feet of aged and deteriorated vitrified clay sewer mains and laterals in Donahue, Becker and Boyce Streets, and replace approximately 130 feet of aged and undersized water mains in Decker St. This project will also replace approx. 785 feet of aged and deteriorated sewer main and laterals in Petaluma Hill Rd. A total of 18 curb ramps will also be upgraded to the curent ADA standards.
04/24/2019Image
Proposed
02229Fire Damage-Related Repairs to Three Pedestrian BridgesRepair three fire-damaged pedestrian bridges: 1) Francis Nielson Park Bridge, 35' x 6' foot wide wooden pedestrian bridge 2) Parker Hill Road Bridge north, 40' x 7' steel pedestrian bridge with wooden deck 3) Parker Hill Road Bridge south, 40' x 7' steel pedestrian bridge with wooden deck
04/23/2019Image
Proposed
00779Franklin Avenue Pedestrian PathConstruct a sidewalk on the west side of Franklin Avenue between Monroe Avenue and Terrace Way. A pedestrian crossing from Terrace Way across Franklin Avenue will be installed along with ADA ramp upgrades.
04/17/2019Image
Proposed
02251Annual Slurry Seal 2019This project will apply slurry seal to various (primarily residential) City streets. Streets are slurried by applying a thin, quarter-inch roadway coating of liquid asphalt and sand. Slurry seal restores the pavement's ability to prevent water intrusion, corrects minor cracking and improves skid resistance. Priorities are established by the Pavement Management System.
04/16/2019Image
Proposed
02137Oakmont Dr. Sewer Main Upsizing Oakmont Creek to Greenfield CirReplace approximately 1188 feet of 6 inch ACP main with 10 inch PVC in Oakmont Drive (Oakmont Creek to Greenfield Circle) as this section is undersized and has resulted in two sanitary sewer overflows since 2009. Pedestrian ramps will be upgraded to current standards within the project limits.
03/05/2019Image
Proposed
01133Cooper Drive Slope Stabilization and Drainage ImprovementsThis project consists of replacing approximately 750 feet of deteriorated concrete lined drainage ditch at the rear of properties located along the east side of Cooper Dr. Drainage and subdrainage improvements will be installed to reduce the potential of future failures.
03/04/2019Image
Proposed
02051Laguna Treatment Plant Primary Influent Pump Drive ReplacementThis project will replace all 6 primary influent pump drives which are critically important for operation of the Laguna Treatment Plant and are now obsolete.
02/13/2019Image
Construction
00780Fulton Rd Reconstruction - Occidental Rd to W 3rd StThis project will reconstruct Fulton Rd. between Occidental Rd. and W. 3rd St. using roller compacted concrete technology, replace deteriorated storm drain pipe near Darla Drive, install a new sewer manhole and update pedestrian ramps to current ADA standards. Roller compacted concrete has the benefit of reduced costs and longer service life. This project will improve safety and reduce ongoing maintenance costs.
02/12/2019Image
Proposed
02254Stony Point Rd Utility Box Adjustments and Sidewalk RepairsComplete sidewalk gap closures and utility box adjustments.
01/31/2019Image
Proposed
02240Minor Work for Water Services Affected by the Tubbs Fire - Cat FApproximately 71 contaminated water service lines at 54 locations were replaced by the Water Department outside of the advisory area in the spring of 2018. The Contractor will return to those locations to perform some additional work that could not be performed by City Crews. The Contractor will replace the existing meter box in kind and install 1 in. Polyethylene coated copper tubing to approximately 12 in. behind the sidewalk to connect to in the future. The contractor will also be replacing the sidewalk at this location. If there is no existing sidewalk, the 1 in. Polyethylene coated copper will be extended to approximately 12 in. beyond the water meter box.
12/11/2018Image
Construction
02150Station 2 Emergency Generator Replacement and Station 3 Power Filter InstallationThis project will install a filter to eliminate harmonic feedback to insure proper operation of the emergency generator at the Station 3 pump station. Additionally, this project will replace the existing emergency generator at Station 2.
10/09/2018Image
Completed
02228Coffey Park- Park Debris RemovalThe initial work, to occur in late November 2018, will remove fire damaged playground equipment, picnic tables, signs, illegally dumped debris and hazardous trees. The park cleanup will be conducted under the same permit process and rules as private property debris removal projects. The park has been tested for hazardous materials, no hazardous materials were detected. However, there is a health and safety risk from small particles of wind and fire blown debris found in the turf areas. For this reason a temporary chain link fence has been installed around the park to reduce the risk of anyone accidentally encountering these materials. The five acres of turf will be remediated in the summer of 2019 when dry weather allows efficient removal of the top 2 to 3 inches of turf and soil.
10/03/2018Image
Construction
02226Metal Beam Guardrail Repair- CitywideMetal Beam Guardrail repair at 8 locations 1. Bicentennial Overcrossing 2.Bicentennial before Fountaingrove 3. Parkerhill north 4. Parkerhill westside 5. Fountaingrove at Hadley Hill 6. Old Redwood at Piner Creek 7. Old Redwood at Fountaingrove Roundbarn Blvd. 8. Rebli Road at Crosscreek
09/12/2018Image
Construction
02101Laguna Treatment Plant Digester Gas Conditioning ImprovementsDigester gas flows to the CHP facility have increased since the commissioning of the High Strength Waste facility. The increased gas flows have shown a need to improve/upgrade certain components of the Plant digester gas conditioning equipment. Design requirements as determined by engineering consultant will be required.
09/04/2018Image
Completed
01996E St Sewer Replacement - 2nd St to Santa Rosa CreekThis project replaces aged and deteriorated clay sanitary sewer main to reduce maintenance needs as well as inflow and infiltration. The new sewer main will also be extended to eliminate issues associated with a lateral that is prone to clogging in the public right of way.
08/08/2018Image
Completed
02206Pavement Preventive Maintenance 2018This project will consist of performing preventive maintenance on City streets by contract. Work to be completed is crack sealing, asphalt dig outs, and pavement resurfacing.
07/18/2018Image
Construction
02059Mendocino Ave and McConnell Ave Intersection Pedestrian ImprovementsConvert the Pedestrian Activated Flasher to a Pedestrian Hybrid Beacon at the intersection of Mendocino Avenue and McConnell Avenue. This would include prohibiting lefts from McConnell westbound to southbound Mendocino Avenue per the corridor plan.
07/17/2018Image
Construction
01582Elizabeth Way Sewer and Water ReplacementThis project is part of the replacement of the Grace neighborhood water and sewer mains. This project will replace undersized and aged water main and aged and obsolete sewer main in Elizabeth Way from Parsons Drive to Town and Country Drive. Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing older deteriorated VCP pipe reduces inflow and infiltration and reduces maintenance costs. Pavement will be reconstructed.
06/28/2018Image
Construction
02004Alvarado Ave and Vallejo St Water and Sewer ImprovementsPhase I will upsize water and sewer mains on Alvarado Avenue and the water main on Vallejo Street between Mt. Olive Drive and Melbrook Way to meet fire flow requirements as identified in the 2014 Water Master Plan. Phase II will improve the sewer junction structure for the Crosstown and Bennett Valley Trunk mains. Two access points will be added to the junction structure to improve visual inspections and facilitate cleaning and maintenance for the entire junction structure and connecting trunk mains.
06/14/2018Image
Completed
01966Montgomery Bridge Sewer Main ProtectionThe sewer main crossing the Montgomery Drive Bridge over Santa Rosa creek is lower than the bottom of the bridge deck and needs protection from debris that could collide into the main when the storm levels in the creek are very high. This project replaces the existing supports with new steel bracing capable of withstanding debris impact and seismic activity.
06/12/2018Image
Completed
02183Temporary Fire Station 5, 3480 Parker Hill RdInstallation of temporary structures on the former Fire Station 5 site to use as a temporary fire station. The project includes: clearing debris and facilities damaged from the Tubbs fire, privacy fence installation, trenching and running utilities to temporary structures, construction of temporary foundations, delivery and assembly of temporary structures, and site improvements necessary to provide disability access.
05/23/2018Image
Completed
02145Accessibility Alterations at Galvin ParkDemolish the existing asphalt pathways around the tennis courts, and replace with new concrete pathways that are accessible to persons with disabilities.

Santa Rosa City Hall - 100 Santa Rosa Avenue - Santa Rosa, CA 95404