Bids List for Capital Improvement Projects

Image Click a project ID number to load the project web page. The project page contains links to bid results, invitation for bids, and the construction plans.
Date BidStatusProjIDTitleDescription
05/17/2017Image
Proposed
01944Sewer Main Lining, Manhole and Lateral Rehab At Various Locations 2016This project will focus on the rehabilitation and/or improvement of sewer mains at various locations in the city. The project will rehabilitate approximately 5,685 feet of pipeline by cured-in-place pipe (CIPP) lining inserted into the existing sewer main pipe at 11 locations throughout the city; 41 manholes are to be rehabilitated and/or improved that are either connected to the pipelines to be CIPP lined or at locations selected by the City; and 6 sewer laterals are to be rehabilitated at three of the project locations.
05/16/2017Image
Proposed
02099Annual Slurry Seal 2017The purpose of this slurry seal project is to restore the pavement's ability to prevent water intrusion, correct minor cracking and improve skid resistance. This procedure includes covering (primarily residential) city streets with a thin, quarter-inch roadway coating of liquid asphalt and sand. Priorities for street selections are established by the Pavement Management System.
05/04/2017Image
Proposed
01952Geysers Pipeline Stabilization - Eastside RoadThis project will address a 150' section of the Geysers pipeline alignment along Eastside Road.
05/04/2017Image
Proposed
01570Spring Lake Lift Station ImprovementsA geotechnical investigation has provided a design scope to repair ground settlement at the Spring Lake Lift Station.  This project will remove several feet of soil and replace it with a suitable compacted granular fill.  Upgrades to the lift station will include new controls, backup generator, lighting, fencing, and a new concrete pad for the station with asphalt concrete pavement on the remainder of the site. 
04/27/2017Image
Proposed
01870Santa Rosa Cmplt Sts Road Diet on Transit CorridorThis project will repave Third Street from 1,100 feet west of Dutton Avenue to the west side of the bridge over Santa Rosa Creek and Mendocino Avenue from Steele Lane to Administration Drive. Upgrade curb ramps to current standards. The Third Street project will include restriping Third Street to a single travel lane in each direction which will allow for a two-way center turn lane and Class-2 bicycle lanes to be provided without removing the street parking. The project striping will continue to provide two travel lanes in either direction at the intersection of Dutton Avenue and Third Street to avoid congestion at the traffic signal.
04/25/2017Image
Proposed
02086Neighborhood Streets Initiative and Roseland Street OverlayThis project will rehabilitate approximately 2.35 miles of selected city streets.  Proposed improvements vary between roadway reconstruction and asphalt concrete overlay at different depth.  All curb ramps within the project limits will be upgraded to the current ADA standards, a total of 80 ramps.  All existing striping will be reinstalled once the streets are resurfaced.
04/12/2017Image
Proposed
01137Bridge Repair - Deck TreatmentProject provides preventive maintenance for concrete bridge decks ensuring long-term durability and prevention of deterioration due to rebar corrosion for six bridges.
12/13/2016Image
Construction
02082Accessibility Alterations at Skyhawk ParkThis project requires removal and reconstruction of approximately 740 lineal feet of existing concrete pathways adjacent to Mountain Hawk Drive; and approximately 400 lineal feet of existing asphalt pathways near the soccer field for the purpose of compliance with the Americans with Disabilities Act. The pathways will be reconstructed within the same footprint as the existing pathways using concrete construction, except for a 25 lineal foot pathway addition to provide disability access to the existing north soccer field. Minor grading is expected at the pathways near the soccer field to correct slope. Grading work will require the removal of two trees growing adjacent to the pathway.
12/07/2016Image
Construction
01807Remove Services from S1 Feed Fountaingrove Pkwy, Mendocino Ave to Round Barn BlvdThe purpose of this project is to remove service from a pump station transmission feed on a Fountaingrove Parkway property and construct a new water segment of water main adjacent to the intersection of Fountaingrove Parkway and Round Barn Boulevard. The roadway pavement will be rehabilitated as needed.
11/09/2016Image
Construction
00468Foley Ave Sewer ImprovementsThe purpose of this project is to provide sewer system improvements consisting of upsizing the existing 6" Sanitary Sewer Main in Foley Ave to an 8" main, as well as redirecting flows from the Old Town trunk to Cleveland Ave. This project will include the installation of water services and 2 new commercial fire hydrants, along with a full road reconstruction.
10/12/2016Image
Construction
01627Downtown Santa Rosa StreetscapeThis project has two locations, one is on 3rd St between Morgan and B St, involving pedestrian improvements including lighting, street trees, bike lanes and delineation to channelize pedestrians to the north side of 3rd St at Morgan St and at B St. The second location is at Santa Rosa Avenue and Mill Street where a new traffic signal will be installed along with pedestrian ramps, and storm drain improvements.
09/21/2016Image
Completed
020532016 Pavement Marking and Montecito Blvd Bike EnhancementsThis project is for the annual contract maintenance installation of edge lines and bike lane lines throughout Santa Rosa. It is intended to ensure bicyclists remain within a bike pathway on the street system by highlighting travel lanes and bike lanes and to provide striping modifications to the street system as needed. In addition, this project will restripe Montecito Blvd. with bike enhancements to connect to the existing Class II bike lanes on Fountaingrove Parkway/Brush Creek Road and continue east to Middle Rincon Road.
09/15/2016Image
Completed
01631Fountaingrove Pkwy Water Main Upsize for High Fire Severity ZoneThe purpose of this project is to replace a section of a water main with a larger diameter pipe, located on Fountaingrove Parkway east of Fir Ridge Drive, in order to increase the water flow to existing reservoirs in a High Fire Severity Zone
07/13/2016Image
Completed
02071Neighborhood Streets Initiative Slurry Seal 2016The project will address paving maintenance on qualifying local and collector streets with slurry seal treatments. These improvements will take place city-wide.

Santa Rosa City Hall - 100 Santa Rosa Avenue - Santa Rosa, CA 95404