Elizabeth Way Sewer and Water Replacement
Estimated Construction Schedule: Slated to begin September, 2018 and is anticipated to be completed January, 2019. Construction Contract Amount: $655,055 Project ID #: 1582 |
Description:
This project is part of the replacement of the Grace neighborhood water and sewer mains. This project will replace undersized and aged water main and aged and obsolete sewer main in Elizabeth Way from Parsons Drive to Town and Country Drive.
Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing older deteriorated VCP pipe reduces inflow and infiltration and reduces maintenance costs. Pavement will be reconstructed.
|
|
Contacts: Mark Kasraie Associate Civil Engineer City of Santa Rosa (707)543-3857 MKasraie@srcity.org Art Carney City Inspector City of Santa Rosa (707)543-3876 Acarney@srcity.org TERRACON CONSTRUCTORS, INC Phone: (707) 433-0323 Correspondence: Advanced Project Notice Other Information: Bid Tab |