Downtown Santa Rosa Streetscape

Estimated Construction Schedule: Slated to begin April, 2017 and is anticipated to be completed July, 2017.
Construction Contract Amount: $641,880
Project ID #: 1627
Description: This project has two locations, one is on 3rd St between Morgan and B St, involving pedestrian improvements including lighting, street trees, bike lanes and delineation to channelize pedestrians to the north side of 3rd St at Morgan St and at B St. The second location is at Santa Rosa Avenue and Mill Street where a new traffic signal will be installed along with pedestrian ramps, and storm drain improvements.

Construction Update Image

Current Activity {July 2017}: The new traffic signal at the intersection of Santa Rosa Avenue and Mill Street is now operating. Work on installation of the lighting and pedestrian improvements on Third Street at the Santa Rosa Plaza will be completed by the end of this month.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

Argonaut Constructors
Phone: (707) 542-4862

Correspondence:
Addendum 1
Invitation for Bids
Plans
C01627 Bid Tab
Imminent Construction Notice
Click for larger image
Project Image

Note: All dates and times are subject to change.