Downtown Santa Rosa Streetscape
Estimated Construction Schedule: Slated to begin April, 2017 and is anticipated to be completed July, 2017. Construction Contract Amount: $641,880 Project ID #: 1627 |
Description:
This project has two locations, one is on 3rd St between Morgan and B St, involving pedestrian improvements including lighting, street trees, bike lanes and delineation to channelize pedestrians to the north side of 3rd St at Morgan St and at B St. The second location is at Santa Rosa Avenue and Mill Street where a new traffic signal will be installed along with pedestrian ramps, and storm drain improvements.
|
|
Contacts: Danny Chen Assistant Engineer City of Santa Rosa (707)543-3911 DChen@srcity.org Argonaut Constructors Phone: (707) 542-4862 Correspondence: Addendum 1 Invitation for Bids Plans C01627 Bid Tab Imminent Construction Notice |