City of Santa Rosa image CIP

Capital Improvement Project


E Haven Dr Sewer and Water Improvements - Eleanor Ave to E Foothill Dr

Estimated Construction Schedule: Slated to begin October, 2023 and is anticipated to be completed April, 2024.
Construction Contract Amount: Pending
Project ID #: 1684
Description: This project is part of the replacement of the Grace neighborhood water and sewer mains. This project will replace undersized and aged water main and aged and obsolete sewer main in East Haven from Eleanor Avenue to East Foothill Drive, in Hawthorne Court, Iris Court and Eleanor Avenue. This project will also replace aged and obsolete sewer main in East Foothill Drive between Thomas Drive and Siesta Lane. Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing older deteriorated VCP pipe reduces inflow and infiltration and reduces maintenance costs. Pavement will be reconstructed.

Construction Update Image

Construction Updates: Argonaut cleaned, pressure tested, hypochlorinated and bacteria sampled the newly installed water mains on East Foothill Dr., Iris Court, Hawthorne Court, Eleanor Ave. and East Haven Drive. Concrete contractor demolitioned sidewalk and pedestrian ramps on Hawthorne Ct. Completion of the sidewalk and pedestrian ramps will proceed as weather permits. City water is scheduled to shut down 02/20/2024 at Eleanor Ave near Pamela Dr. to abandon the exisiting 6" water main and tie-in the new 8" water main, followed by transfering of water services of 1929, 1930, 1936, 1942, 2022, 2030, 2033 and 2035 Eleanor Ave. Prior to Shut Down, City Workers will let residents know the day of. More shutdowns scheduled in the following weeks.

Contacts:

Sara Mathews
Associate Civil Engineer
City of Santa Rosa
(707)543-3866
SMathews@srcity.org

Charles Robinson
Civil Engineering Tech III
City of Santa Rosa
+1 (707) 791-5978
CRobinson@srcity.org

Tom Gorman
Construction Manager
Kennedy Jenks
707-888-8064

Cody Bedell
Contractor Project Manager
Argonaut Constructors
707-332-3306

Correspondence:
Bid Tabs C01684
Advance Project Notice - English
Advance Project Notice - Spanish
Imminent Construction Notice - English
Imminent Construction Notice - Spanish
Click for larger image
Project Image

Note: All dates and times are subject to change.