City Hall Plaza Demonstration Garden and LID Retrofit

Estimated Construction Schedule: Slated to begin August, 2016 and is anticipated to be completed February, 2017.
Construction Contract Amount: $1,144,240
Project ID #: 1931
Description: The City of Santa Rosa has received a State Water Resources Control Board Stormwater Grant. The project will convert two of the large lawn areas at City Hall to a low water use demonstration garden and retrofit the main parking lot to capture and treat stormwater runoff. Additionally, this project will include a rainwater harvesting demonstration feature, a public gathering area for educational classes, signage and kiosks throughout the campus, as well as a web-based educational interface.

Construction Update Image

Current Activity:: Construction began on this project on August 8, 2016. Please click on the following link for more information on this project and the Sustainable Education Garden:


Debra Lane
Sustainability Representative
City of Santa Rosa

Dale Tressler
Quality Control Associate
City of Santa Rosa

Richard Owens
Siri Grading And Paving, Inc

Rich Siri
Siri Grading And Paving, Inc

Other Information:
Invitation for Bids
Bid Tab Results
Click for larger image
Project Image

Note: All dates and times are subject to change.