Lower Colgan Creek Restoration Phase 3
Estimated Construction Schedule: Slated to begin June, 2025 and is anticipated to be completed November, 2025. Construction Contract Amount: Pending Project ID #: 1946 |
Description:
This information is for Phase 3 of a planned 3 phase project. Project limits are from Boron Avenue downstream to Dutton Meadow.
This restoration project will restore 2,450 linear feet of straightened and denuded channel into a natural creek while still providing flood protection. The new alignment will allow the creek channel to have greater water retention during high demands. There will be structures and pools installed to enhance aquatic life such as boulders, boulder weirs, and over 1,000 native trees, shrubs and grasses.
Human elements include the creation of a bicycle/pedestrian path and pedestrian bridge.
|
|
Contacts: Gregory Dwyer Associate Civil Engineer City of Santa Rosa (707)543-3838 GDwyer@srcity.org Charles Robinson Civil Engineering Tech III City of Santa Rosa +17077915978 CRobinson@srcity.org Correspondence: C01946 Invitation for Bids (for information only-see PlanetBids for bidding) C01946 Plans (for information only - see PlanetBids for bidding) Advance Project Notice - English Advance Project Notice - Spanish Bid Tabs |