Capital Improvement Project


Underground Tank Remediation 650 4th Street

Estimated Construction Schedule: Slated to begin August, 2016 and is anticipated to be completed November, 2017.
Construction Contract Amount: Pending
Project ID #: 2007
Description: To investigate what is suspected to be an old, unpermitted heating oil tank under the sidewalk in front of 650 4th Street. If it is a tank, then it will be abandoned under Fire Department oversight.

Construction Update Image

Current Activity {November 2017}: The tank has been abandoned and the excavation backfilled. This project will be complete after the sidewalk is repaired, which is scheduled for the first week of December 2017.

Contacts:

Christopher Catbagan
Associate Civil Engineer
City of Santa Rosa
(707)543-4521
ccatbagan@srcity.org

Chad Anderson
Quality Control Associate
City of Santa Rosa

CAnderson@srcity.org
Click for larger image
Project Image

Note: All dates and times are subject to change.