Llano Trunk Lining - W College Utilities Facility
Estimated Construction Schedule: Slated to begin August, 2019 and is anticipated to be completed October, 2020. Construction Contract Amount: Pending Project ID #: 2042 |
Description: This project will rehabilitate approximately 1,100 feet of pipeline by cured-in-place pipe (CIPP) lining inserted into the existing sewer main pipe, located within the W. College Utilities Facility. Six manholes will be rehabilitated a corrosion resistant epoxy liner for protection against future hydrogen sulfide deterioration. | |
Contacts: Bryan Heinzelman Associate Civil Engineer City of Santa Rosa (707)543-3812 BHeinzelman@srcity.org Correspondence: Imminent Construction Notice Imminent Construction Notice - Spanish Other Information: C02042 Bid Results C02042 Invitation for Bids (for information only - see PlanetBids for bidding) |