Annual Slurry Seal 2016

Estimated Construction Schedule: Slated to begin July, 2016 and is anticipated to be completed September, 2016.
Construction Contract Amount: $357,027
Project ID #: 2054
Description: The purpose of this slurry seal project is to restore the pavement's ability to prevent water intrusion, correct minor cracking and improve skid resistance. This procedure includes covering (primarlily residential) city streets with a thin, quarter-inch roadway coating of liquid ashphalt and sand. Priorities for street street selections are established by the Pavement Management System.

Construction Update Image

Construction Update: Work ended 8/19/2016.

Contacts:

Clay Thistle
Associate Civil Engineer
City of Santa Rosa
(707)543-3855
CThistle@srcity.org

Ed Skultety
Civil Engineering Technician III
City of Santa Rosa
(707) 543-3877
ESkultety@srcity.org

Correspondence:
Advance Project Notice
Advance Project Notice - Spanish
Imminent Construction Notice
Imminent Construction Notice- Spanish

Other Information:
C02054 IFB
Bid Results
Click for larger image
Project Image

Note: All dates and times are subject to change.