Laguna Treatment Plant Digester Gas Conditioning Improvements
Estimated Construction Schedule: Slated to begin September, 2018 and is anticipated to be completed December, 2018. Construction Contract Amount: Pending Project ID #: 2101 |
Description: Digester gas flows to the CHP facility have increased since the commissioning of the High Strength Waste facility. The increased gas flows have shown a need to improve/upgrade certain components of the Plant digester gas conditioning equipment. Design requirements as determined by engineering consultant will be required. | |
Contacts: Emma Walton Water Reuse Engineer City of Santa Rosa (707)543-4516 ewalton@srcity.org Other Information: C02101 Invitation for Bids (Information only - see PlanetBids for bidding) C02101 Plans C02101 Bid Results |