Estimated Construction Schedule: Slated to begin August, 2025 and is anticipated to be completed October, 2025.
Construction Contract Amount: Pending
Project ID #: 2121
Description: Leete Well is to be rehabilitated to expand the City's emergency water supply as outlined in the Ground Water Master Plan. An evaluation of the well casing and building is necessary to determine project scope and associated costs.

Construction Update Image

December 2024: The Leete Well is being cleaned to maintain emergency water supply infrastructure which is vital for our community. Work will continue in early January and is weather dependent. Thank you for your patience.

Contacts:

Lucas Bishop
Assistant Engineer
City of Santa Rosa
(707)543-3861
LBishop@srcity.org

Jim Strandberg
Designer Project Manager
Woodard & Curran
925-627-4122

Angel Vargas
City Inspector
City of Santa Rosa
707-543-4608

Correspondence:
C02121 Imminent Construction Notice 1 - English
C02121 Imminent Construction Notice 1 - Spanish
Click for larger image
Project Image

Note: All dates and times are subject to change.