Station 2 Emergency Generator Replacement and Station 3 Power Filter Installation
Estimated Construction Schedule: Slated to begin February, 2019 and is anticipated to be completed July, 2020. Construction Contract Amount: $333,333 Project ID #: 2150 |
Description: This project will install a filter to eliminate harmonic feedback to insure proper operation of the emergency generator at the Station 3 pump station. Additionally, this project will replace the existing emergency generator at Station 2. Project is near completion. | |
Contacts: Tracy Duenas Supervising Engineer City of Santa Rosa (707)543-3952 TDuenas@srcity.org Other Information: Invitation for Bids (information only - see PlanetBids for bidding) Plans Bid Tab |
Click for larger image![]() |