Emergency Storm Drain Repair- Melbrook Way

Estimated Construction Schedule: Slated to begin October, 2017 and is anticipated to be completed December, 2017.
Construction Contract Amount: $100,000
Project ID #: 2161
Description: The purpose of this emergency project is to repair a failed storm drain outfall and restabilize the creek bank using rip-rap armoring. Construction work is scheduled for approximately 10 working days (weather permitting). Work began on Monday, October 30, 2017.

Construction Update Image

Construction Update: Project complete 12/07/2017.