City of Santa Rosa image CIP

Capital Improvement Project


Fire-Related Repairs of Utility Stations

Estimated Construction Schedule: Slated to begin July, 2020 and is anticipated to be completed July, 2021.
Construction Contract Amount: $1,398,000
Project ID #: 2208
Description: Several potable water stations, reservoirs and sewer lift stations sustained damage during the Tubbs Fire. This project will undertake rehabilitation efforts at the affected sites.

Construction Update Image

Current Activity September 2021: Pacific Infrastructure Corporation has completed the Fencing, Gate and Signage installations at various locations. The Replacement Generator at Sewer Lift Station 1 on Stagecoach Road is in service. There is minor outstanding work to be performed at the Stagecoach site prior to completing this project.

Contacts:

Eric Frye
Quality Control Associate
City of Santa Rosa
(707)543-3858
EFrye@srcity.org

Correspondence:
C02208 Invitation for Bids (for information only - see PlanetBids for bidding)
C02208 Plans (for information only-see PlanetBids for bidding)
Bid Tabs
Imminent Construction Notice-English
Imminent Construction Notice-Spanish
Project Limits Map
Click for larger image
Project Image

Note: All dates and times are subject to change.