Replacement of Water Services Outside Advisory Area

Estimated Construction Schedule: Slated to begin June, 2018 and is anticipated to be completed March, 2019.
Construction Contract Amount: $604,290
Project ID #: 2213
Description: This project will remove and replace the water services damaged by the Tubbs Fire with new 1 in. Polyvinyl Copper Services from the water main to the meter to properties located outside the Advisory Area.

Construction Update Image

Construction Update - March 2019: Construction is nearly complete. Minor punchlist items remain.

For questions related to Water Quality:: For more specific information regarding the sampling results at or near your property, Please contact the Water Department at waterquality@srcity.org or go to the interactive map on the website with the latest sampling data, which can be accessed from www.srcity.org/wqadvisory.

Contacts:

Jillian Tilles
Associate Civil Engineer
City of Santa Rosa
(707)543-3878
jtilles@srcity.org

Shirlee Stiles
Civil Engineering Tech III
City of Santa Rosa

SStiles@srcity.org

Correspondence:
Invitation for Bid
Boundary Map
Advance Construction Notice
Advance Construction Notice - Spanish
Imminent Construction Notice
Imminent Construction Notice - Spanish

Other Information:
Bid Tab


Tell Us How We Did Image

Click for larger image
Project Image

Note: All dates and times are subject to change.