Coffey Park- Park Debris Removal and Soil Remediation

Estimated Construction Schedule: Slated to begin December, 2018 and is anticipated to be completed January, 2019.
Construction Contract Amount: Pending
Project ID #: 2228
Description: Demo the existing Coffey Park features, remove contaminated soil and remaining trees/debris. Regrade the site to facilitate construction of a new park.

Construction Update Image

Current Activity July 2018: This month the process to secure the park with perimeter fencing in preparation of a debris removal project was initiated. The debris removal scope and schedule depends on results of hazardous meterials testing expected in early August.

Contacts:

Gregory Dwyer
Associate Civil Engineer
City of Santa Rosa
(707)543-3838
GDwyer@srcity.org
Click for larger image
Project Image

Note: All dates and times are subject to change.