City of Santa Rosa image CIP

Capital Improvement Project


Six Fire Damaged Parks- Recovery

Estimated Construction Schedule: Slated to begin May, 2022 and is anticipated to be completed November, 2022.
Construction Contract Amount: $1,471,254
Project ID #: 2248
Description: This is project is a fire recovery project involving 6 city parks that were partially destroyed during the Tubbs Fire in 2017. The affected parks are Fir Ridge Park, Francis Nielsen Park, Nagasawa Park, Rincon Ridge Park, Rincon Ridge Open Space, and Parker Hill Open Space. The intended purpose of this project is to restore all parks to their pre fire condition with the exception of code-related upgrades. Additionally, as a result of community feedback, a new playground facility will be installed at Fir Ridge Park.

Construction Update Image

May 2022: This project was awarded to Oak Grove Construction of Petaluma on 2/22/2022. The construction is slated to being in early May when all required submittals are approved. This project has a total duration of 120 working days (about 6 months). With this duration, all 6 park locations are anticipated to start concurrently. Such approach will help expedite the completion of the overall construction in 6 months and help minimize public inconvenience. Please also note that certain facilities required long lead time on manufacturing process and however long it may take is beyond contractor and the city's control so additional time of completion may be impacted. An example of such delay would be the palyground equipment. During the construction period and unless if the area of any park is fenced partially or entirely, some parks will remain open to public. Exception to Fir Ridge Park which shall remained closed until project is complete. As a safety precaution, please be aware that even if parks remain open concurrently with an active construction nearby, construction vehicles will be sharing the same roadways that park visitors use.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

Ryan Curry
Inspector/Construction Manager
MCK America Inc.
(415)656-3264
Rcurry@mckinc.net

Grant Bailey
Supervising Engineer
City of Santa Rosa
(707)543-4508
Gbailey@srcity.org

Correspondence:
Advance Project Notice
Advance Project Notice - Spanish
Imminent Construction Notice
Imminent Construction Notice - Spanish

Other Information:
C02248 Invitation for Bids (for information only - see PlanetBids for bidding)
C02248 Plans
Bid Tabs
Click for larger image
Project Image

Note: All dates and times are subject to change.