City of Santa Rosa image CIP

Capital Improvement Project


Backup Generators - Water and Wastewater Facilities

Estimated Construction Schedule: Slated to begin October, 2022 and is anticipated to be completed September, 2024.
Construction Contract Amount: Pending
Project ID #: 2256
Description: This project will replace existing emergency generators and related equipment at 18 water and wastewater facilities in and around Santa Rosa. These upgrades increase generator capacities, update aging equipment, transition facilities to more reliable fuel sources, and decrease greenhouse emissions. This project is part of our larger and ongoing efforts to harden the City's critical infrastructure against potential future hazards, and is funded in part by grants secured from FEMA and the California Office of Emergency Services.
Contacts:

Gregory Dwyer
Associate Civil Engineer
City of Santa Rosa
(707)543-3838
GDwyer@srcity.org

Charles Robinson
Civil Engineering Tech III
City of Santa Rosa
+1 (707) 791-5978
CRobinson@srcity.org

Brian Lydon
TERRACON CONSTRUCTORS, INC
(707)484-8010

Michael Lydon
TERRACON CONSTRUCTORS, INC
(707)480-3816

Correspondence:
Advance Project Notice All Sites - English
Advance Project Notice All Sites - Spanish
C02256_BidTabsRevised
Click for larger image
Project Image

Note: All dates and times are subject to change.