Capital Improvement Project


Sonoma Ave Pavement Rehabilitation - E St to Bobelaine Dr

Estimated Construction Schedule: Slated to begin October, 2023 and is anticipated to be completed May, 2024.
Construction Contract Amount: Pending
Project ID #: 2262
Description: This rehabilitation project includes grinding out and/or overlaying approximately 0.9 center line miles of this roadway with hot mixed asphalt due to failing and deteriorating pavement conditions. Existing Class II bike lanes will be maintained and pedestrian ramps will be reconstructed to current ADA standards. Approximately 75 Water services within the project limits will be replaced.

Construction Update Image

Construction update: Week of 4/29/24: Paving has been completed in all areas. Utility access boxes/ lids will now be brought to grade, followed by permanent striping of the new roadway. Please pay attention to posted parking restriction, detours, and road work signs.

Contacts:

Gregory Dwyer
Associate Civil Engineer
City of Santa Rosa
(707)543-3838
GDwyer@srcity.org

Charles Robinson
Civil Engineering Tech III
City of Santa Rosa
+17077915978
CRobinson@srcity.org

Tom Gorman
Construction Manager
Kennedy Jenks
1-707-888-8064
tomgorman@kennedyjenks.com

Casey Wood
Project Manager
Ghilotti Brothers
1-628-234-5404
caseyw@gbi1914.com

Correspondence:
C02262 Invitation for Bids (for information only-see PlanetBids for bidding
C02262 - Plans (for information only-see PlanetBids for bidding)
Bid Tabs C02262


SB1 Image

Click for larger image
Project Image

Note: All dates and times are subject to change.