City of Santa Rosa image CIP

Capital Improvement Project


West College Storage Facility Pumping Improvements

Estimated Construction Schedule: Slated to begin August, 2020 and is anticipated to be completed October, 2020.
Construction Contract Amount: Pending
Project ID #: 2284
Description: West College Wet Weather Facility storage basins allow the City to temporarily divert storm flows from the local system in order to balance flows in the Laguna Treatment Plant during winter storm events. Currently, the City rents two trailer mounted diesel powered, vacuum assisted pumps and places them in position at the West College Storage Facility. The City plans to purchase two mobile pumps of similar capacity in lieu of renting and desires to construct permanent facilities to house and operate the pumps including a pad (with built-in containment), roof cover and connection to existing bypass piping.
Contacts:

Andrew Wilt
Associate Civil Engineer
City of Santa Rosa
(707)543-3878
awilt@srcity.org

Michael Mirich
Civil Engineering Tech III
City of Santa Rosa
+1 (707) 481-9395
MMirich@srcity.org

Dave Coleman
Consultant Design Engineer
Brelje and Race
707) 636-3756
coleman@BRCE.com
Click for larger image
Project Image

Note: All dates and times are subject to change.