Fire-Damaged Tree Removal- Parks, Open Space, ROW

Estimated Construction Schedule: Slated to begin August, 2020 and is anticipated to be completed October, 2020.
Construction Contract Amount: $109,296
Project ID #: 2287
Description: This project is a second phase of fire damaged hazardous tree project and will remove approximately 150 trees within city owned parcels. Concurrenlty, an arborist will be inspecting additonal trees in the burn area that have not been evaluated to identify trees for a third removal contract.

Construction Update Image

November 2020: This project is complete.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

Greg Loraditch
Civil Engineer Technician III
City of Santa Rosa
(707)543-3875
Gloraditch@srcity.org

Josh Johns
Project Manager
ARBORIST NOW, INC
josh@arboristnow.com

Correspondence:
Imminent Construction Notice
Imminent Construction Notice - Spanish
Location Map

Other Information:
Invitiation for Bid (for information only - See PlanetBids for Bidding)
Bid Tabs
Addendum 1 (for information only)
Addendum 2 (for information only)
Addendum 3 (for information only)
Click for larger image
Project Image

Note: All dates and times are subject to change.