Leland St Storm Drain and Creek Bank Repair
Estimated Construction Schedule: Slated to begin November, 2019 and is anticipated to be completed December, 2019. Construction Contract Amount: $66,268 Project ID #: 2288 |
Description:
This project repairs an existing damaged culvert at the end of Leland St which discharges into Santa Rosa Creek, and secures a bank failure and subsequent slide. Additionally, several trees have fallen as a result of the slide and the existing guard rail has been damaged. This project will repair the damaged storm drain sections, restore the creek bank, remove the fallen trees, and repair the damaged guard rail.
|
|
Contacts: Sara Mathews Assistant Engineer City of Santa Rosa (707)543-3866 SMathews@srcity.org James Piazza Construction Manager (707)876-3410 Correspondence: Advanced Project Notice Advanced Project Notice - Spanish Imminent Construction Notice Imminent Construction Notice - Spanish |