Capital Improvement Project


Fire Damaged Roadway Landscaping

Estimated Construction Schedule: Slated to begin August, 2022 and is anticipated to be completed October, 2023.
Construction Contract Amount: $6,009,025
Project ID #: 2300
Description: This project will remove and replace fire damaged irrigation components within City right of way in the Coffey Park and Fountaingrove neighborhoods.

Construction Update Image

September 2023: The primary focus of the current construction activities is to complete the planting requirements by October 12, 2023. Traffic along Fountaingrove Pkwy is anticipated to be more congested then normal because of the planting activities and the manual water truck activities that are taking place simutaneously. All lane closure hours are limited between 8:30 am and 4:00 pm and one lane for each direct will be maintained to allow traffic flow.

Other info: Stolen Plants: Ever since the start of the planting event in Mid-August to date, 54 plants and 1 tree have been stolen after they were planted onsite along the medians and the planter strips area on Fountaingrove Parkway between Stagecoach Rd and Day Break Ct. Please be on a look out for the community and report any suspicious activities to Santa Rosa Police Department at (707)528-5222. Thank you for your help and be safe out there.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

Jason Balatti
Construction Manager
Green Valley Consulting Engineers
(707)579-0388
JasonB@Gvalley.com

Greg Mariscal
Supervising Engineer
City of Santa Rosa
(707)543-3832
Gmariscal@srcity.org

Other Information:
C02300 Invitation for Bids (for information only - see PlanetBids for bidding)
Bid Tabs
C02300 Plans (for information only - see Planet Bids for bidding)
Click for larger image
Project Image

Note: All dates and times are subject to change.