City of Santa Rosa image CIP

Capital Improvement Project


Water Tanks Tree Removal

Estimated Construction Schedule: Slated to begin January, 2023 and is anticipated to be completed March, 2023.
Construction Contract Amount: Pending
Project ID #: 2305
Description: This project will evaluate trees at five Water facilities to determine whether they pose a hazard to the tank, other infrastructure, or public safety. Identified hazard trees will be removed.

Construction Update Image

Project Updates for April 2023: Atlas Tree will be doing tree removal at 476 Woodley Place on Friday.

Contacts:

Sara Mathews
Assistant Engineer
City of Santa Rosa
(707)543-3866
SMathews@srcity.org

Oscar Serrano
Inspector
City of Santa Rosa
(707)543-3844
OSerrano@srcity.org

Corin Burns
Contractor Project Manager
Atlas Tree
(707)523-4399
corin@atlas-tree.com

Correspondence:
C02305 Invitation for Bids (For information only - see PlanetBids for bidding)
Bid Tabs
ICN-1395 Fountaingrove Pkwy English
ICN-1395 Fountaingrove Pkwy Spanish
ICN-3899 Parker Hill Rd English
ICN-Parker Hill Rd Spanish
ICN-4177 Chanate Rd English
ICN-4177 Chanate Rd Spanish
ICN-5035 Harville Rd English
ICN-5035 Harville Rd Spanish
ICN-Proctor Tank English
ICN-Proctor Tank Spanish
Click for larger image
Project Image

Note: All dates and times are subject to change.