Traffic Signalization at Hearn Ave at Burbank Ave

Estimated Construction Schedule: Slated to begin October, 2024 and is anticipated to be completed March, 2025.
Construction Contract Amount: Pending
Project ID #: 2319
Description: Project will install a four-way traffic signal, with 2 traffic poles with mast arms, 6 single traffic pole, Opticom (video cameras) on all four approaches, pedestrian crossings on the south and east legs, lane striping, advanced loop detection east and west of the intersection on Hearn Ave. A proposed traffic signal will increase the traffic handling capacity of the intersection and will improve the safety & efficiency of both pedestrian and vehicular traffic. Project will improve access to park for pedestrians and vehicles.
Contacts:

Jose Mederos Baltazar
Assistant Engineer
City of Santa Rosa
(707)543-3915
JMederos@srcity.org

Marcial Gonzalez
Quality Control Associate
City of Santa Rosa
+1 (707) 953-7298
mgonzalez@srcity.org
Click for larger image
Project Image

Note: All dates and times are subject to change.