Garage Hoist Purchase and Installation
Estimated Construction Schedule: Slated to begin March, 2025 and is anticipated to be completed May, 2025. Construction Contract Amount: Pending Project ID #: 2354 |
Description: Two (2) in-ground and two (2) above ground heavy duty vehicle lifts in the garage need to be replaced. 78,000 lift capacity with 40' lengths. Work will require excavating the old units, cleaning up any oil contaminated soils, then installing foundations, a sealed vault" type lift that would contain any spills. | |
Contacts: Jose Mederos Baltazar Assistant Engineer City of Santa Rosa (707)543-3915 JMederos@srcity.org Marcial Gonzalez Quality Control Associate City of Santa Rosa +1 (707) 953-7298 mgonzalez@srcity.org |
Click for larger image |