City of Santa Rosa image CIP

Capital Improvement Project


Sidewalk Survey and Maintenance

Estimated Construction Schedule: Slated to begin October, 2019 and is anticipated to be completed December, 2019.
Construction Contract Amount: Pending
Project ID #: 700
Description: This project will survey and repair minor sidewalk lifts utilizing a horizontal saw cutting method at various locations within Santa Rosa. The sidewalk saw cutting/repairs are not expected to last longer than 15 minutes at each location. Pedestrian traffic may be affected for this short time and detours are expected to be provided to the pedestrain by the contractor. The working hours will vary but will be between 7am-3pm.

Construction Update Image

Current Activity {October 2019}: 9/26/2019: The Sidewalk Survey is scheduled to start on October 7, 2019. This assessment phase is expected to take approximately 2 weeks (rl). >>> 10/09/2019: The sidewalk survey for the Railroad Square Business District will be completed today. The contractor will then be moving to the Downtown Business District area (rl).

Project Limits: The project locations will be in the Downtown & Railroad Square business districts.

Contacts:

Lisa Welsh
Associate Civil Engineer
City of Santa Rosa
(707)543-3909
LWelsh@srcity.org

Robert Townsend
Operations Supervisor
StreetPlus
(707) 318-7777
RTownsend@streetplus.net
Click for larger image
Project Image

Note: All dates and times are subject to change.