City of Santa Rosa image CIP

Capital Improvement Project


Howarth Courts Renovation

Estimated Construction Schedule: Slated to begin October, 2025 and is anticipated to be completed December, 2026.
Construction Contract Amount: Pending
Project ID #: 714
Description: Resurface tennis courts at Howarth Park including tennis/pickle court reconfiguration.

Construction Update Image

July (Construction Update): As the warm weather continues, the drying process for the subgrade was a success, which allowed the contractor to install the asphalt concrete for the new court surface and meeting the required compaction testings. With a steady dry weather condition, the project is slated for completion around mid September.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

Ivan Ayres
Inspector
Coastland DCCM
(707)636-7020
iayres@dccm.com

Correspondence:
C00714 Invitation for Bids (for information only - see PlanetBids for bidding)
C00714 Plans (for information only - see PlanetBids for bidding)
Bid Tabs C00714
Click for larger image
Project Image