Howarth Courts Renovation

Estimated Construction Schedule: Slated to begin October, 2025 and is anticipated to be completed December, 2026.
Construction Contract Amount: Pending
Project ID #: 714
Description: Resurface tennis courts at Howarth Park including tennis/pickle court reconfiguration.

Construction Update Image

March (Construction Update): March 2, 2026 marks the first day of the court renovation. DMR (Contractor) will begin by installing a temporary construction fencing around the entire tennis/pickleball courts area for the entire duration of the project that is slated for completion by June or July month depending on the manufacturing process of certain contract items of work. During the period of construction, all areas near the existing courts which will be fenced off are considered as off-limit to the general public 24/7. A few parking spots near the courts and within the park will also be fenced off from access for safety reasons. The normal construction hours are limited to between 7:00 am to 4:30 pm, Monday to Friday. During the construction hours, all construction vehicles will share the same entrance and exit routes with the normal park goers, so please be extra careful for being near an active construction site as either pedestrians or the motorist. Thank you for your patience and understanding.

Basic Information: Construction starts on 3/2/26.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

To be determined.

Correspondence:
C00714 Invitation for Bids (for information only - see PlanetBids for bidding)
C00714 Plans (for information only - see PlanetBids for bidding)
Bid Tabs C00714
Click for larger image
Project Image

Note: All dates and times are subject to change.