Capital Improvement Project


Stony Point Road Widening and Reconstruction Phase 2 - Sebastopol Road to Hearn Ave

Estimated Construction Schedule: Slated to begin August, 2015 and is anticipated to be completed December, 2017.
Construction Contract Amount: $10,002,039
Project ID #: 727
Description: The purpose of this project will be to ease traffic congestion by widening Stony Point Road to four lanes from Hearn Avenue to Sebastopol Road. The addition of travel and turn lanes, new sidewalks, bicycle lanes, and updated traffic signal upgrades will increase road safety along this vital north-south corridor. The project also includes the installation of new water main and water services, sewer main stubs to currently undeveloped parcels and storm drains.

Construction Update Image

ROAD WIDENING AND RECONSTRUCTION WORK IS UNDERWAY: Construction of this roadway widening project is now underway. For your convenience, a special website and social media pages have been created to help keep you informed about this project.

Website: stonypointroad.com
Twitter: twitter.com/SR_PublicWorks
Facebook: facebook.com/stonypointroad

During construction there will be traffic control and detours. At times access to sidewalks and street parking may be restricted or closed. Night work may be necessitated in order to lessen impacts during peak commute hours.

Traffic Delays Expected on Stony Point Road September 11-29, 2017: The next phase in the paving operation along the Stony Point Road corridor is moving to the west side of the roadway from Mesa Way to Pearblossom Drive. This phase will begin Monday, September 11 and continue through September 29. Construction crews will be grading and paving the roadway and traffic will be heavily impacted.

Stony Point Road will remain open at all times, with flaggers in place to assist traffic at inter-sections as needed. All schools and businesses in the area will be OPEN during construction. Take alternate routes if possible.

If you have any questions or concerns about construction activities, please call the project hotline at 707-535-0799. To view a map of the paving area, visit www.stonypointroad.com.

Contacts:

Steve Dittmer
Supervising Engineer
City of Santa Rosa
(707)543-3847
SDittmer@srcity.org

Mimi Arvin
Construction Manager
City of Santa Rosa
(707)543-3914
marvin@srcity.org

Ben Weeks
Superintendent
BAY CITIES PAVING & GRADING
(925)270-9922
bweeks@baycities.us

Correspondence:
Imminent Construction Notice 08-18-15
Bay Cities - Imminent Construction Notice 08-18-15


Measure M Image

Click for larger image
Project Image

Note: All dates and times are subject to change.