City of Santa Rosa image CIP

Capital Improvement Project


Remove Services from S1 Feed Fountaingrove Pkwy, Mendocino Ave to Round Barn Blvd

Estimated Construction Schedule: Slated to begin February, 2017 and is anticipated to be completed April, 2017.
Construction Contract Amount: $236,173
Project ID #: 1807
Description: The purpose of this project is to remove service from a pump station transmission feed on a Fountaingrove Parkway property and construct a new water segment of water main adjacent to the intersection of Fountaingrove Parkway and Round Barn Boulevard. The roadway pavement will be rehabilitated as needed.

Construction Update Image

May, 2017: Construction is complete.

Contacts:

Andy Allen
Supervising Engineer
City of Santa Rosa
(707)543-4291
AAllen@srcity.org

Randy Inselman
Civil Engineering Tech III
City of Santa Rosa
(707) 321-9845
RInselman@srcity.org

Correspondence:
Bid Tabs
Advance Construction Notice
Imminent Construction Notice

Other Information:
C01807 IFB
C01807 Plans
Click for larger image
Project Image

Note: All dates and times are subject to change.