Bids List for Capital Improvement Projects

Image Click a project ID number to load the project web page. The project page contains links to bid results, invitation for bids, and the construction plans.
Date BidStatusProjIDTitleDescription
06/21/2022Image
Proposed
02388Public Safety Building Hydronic Pipeline ReplacementThis project will replace the Public Safety Building (955 & 965 Sonoma Ave) hot and cold water supply and return lines for the building's hydronic boiler system.
06/07/2022Image
Construction
02192Laguna Treatment Plant Emergency Generator Fuel Tank and Fleet Fueling Station ReplacementThe outer wall of the existing emergency generator diesel fuel storage tank has started to deform preventing monitoring of the annual space. The tank is now out of compliance from a regulatory standpoint and needs to be replaced. The fuel storage tank is critical to insuring operation of the plant in the event of a power outage.
06/01/2022Image
Proposed
02111Geysers - Delta Connection ImprovementsUpsize approximately 130 linear feet of the existing 12" diameter connection between the Geysers Pipeline and Delta Pond to 24" diameter. This will allow high flows of recycled water to be delivered to Delta Pond using the Geysers pipeline as a redundant supply line to the reclamation piping network.
04/28/2022Image
Proposed
02311Crosstown Trunk Lining - 3 SegmentsThis project aims to extend the useful life of a portion of the cross-town trunk sewer. CCTV observations have identified corrosion at the crown of the pipe. The project will examine various options for structural rehabilitation and then engage a contractor to perform the rehab work. Rehabilitation work will be performed at three locations along the trunk.
04/12/2022Image
Construction
02052Controller and Radio Upgrades at Water Pump Stations and Sewer Lift StationsUpgrade programmable logic controllers for all water stations, radio systems for all water and sewer stations to standardized equipment and develop a program to replace them on a regular basis. Currently different hardware and software exists at the stations and local operations has experienced communications errors between station and tanks.
04/07/2022Image
Construction
02041Cleveland Ave & St Rose District Sewer & Water ImprovementsThis project will abandon approximately 700 feet of clay sewer main on the west side of Cleveland between Ridgway Avenue and Carrillo Street by transferring 23 laterals to an existing PVC sewer trunk on the east side of Cleveland Avenue. Additionally, this project will include sewer system improvements for 7th Street and B Street. The work on 7th Street will abandon 540 feet of clay sewer main and transfer 2 laterals to an existing sewer trunk between A Street and B Street. The work on B Street includes replacing a 30-foot section of deteriorated pipe near Healdsburg Avenue. This work will reduce inflow and infiltration and reduce maintenance costs.
03/29/2022Image
Construction
00284Laguna Treatment Plant Disinfection Improvements ProjectUltraviolet light (UV) is the primary disinfection process for the City of Santa Rosa's Laguna Treatment Plant (LTP). The existing system was commissioned in 1998, has reached the end of its useful life, and no longer has the treatment capacity for peak wet weather sewer flows. This project will replace the existing UV system with a new UV system. Additionally, this project will install an effluent diversion pump station and pipeline to convey effluent to the beginning of the plant for retreatment. This provides greater flexibility for operations and regulatory compliance.
03/15/2022Image
Construction
00327Terra Linda and Buena Vista Sewer and Water Replacement - Phase 1This project will upgrade existing 6-inch water mains along Terra Linda Dr. to remediate fire flow deficiencies. Aged sewer mains (1961) will be replaced congruently to minimize the potential for future deficiencies. Water and Sewer mains in Terra Linda Ct. will also be replaced. The pavement will be reconstructed along Terra Linda Dr. to Buena Vista and in Terra Linda Ct. once mains have been replaced. ** Note: This project is separate from PID00158 North Trunk Sewer Replacement -Mendocino Ave to Terra Linda Dr
03/08/2022Image
Proposed
01178Fulton Rd from Guerneville Rd to Piner Rd - Widen to Four LanesThe purpose of this project is to ease future traffic congestion. Fulton Road will be reconstructed and widened to 4 lanes with bike lanes and sidewalks between Guerneville Road and Piner Road. The Project includes PG&E Rule 20A underground district, roller compact paving, 2 travel lines in each direction, widen sidewalk, bike lanes, median islands and storm drain improvements.
02/08/2022Image
Proposed
02300Fire Damaged Roadway LandscapingThis project will remove and replace fire damaged irrigation components within City right of way in the Coffey Park and Fountaingrove neighborhoods.
01/11/2022Image
Proposed
02248Six Fire Damaged Parks- RecoveryThis is project is a fire recovery project involving 6 city parks that were partially destroyed during the Tubbs Fire in 2017. The affected parks are Fir Ridge Park, Francis Nielsen Park, Nagasawa Park, Rincon Ridge Park, Rincon Ridge Open Space, and Parker Hill Open Space. The intended purpose of this project is to restore all parks to their pre fire condition with the exception of code-related upgrades. Additionally, as a result of community feedback, a new playground facility will be installed at Fir Ridge Park.
11/30/2021Image
Construction
02284West College Storage Facility Pumping ImprovementsWest College Wet Weather Facility storage basins allow the City to temporarily divert storm flows from the local system in order to balance flows in the Laguna Treatment Plant during winter storm events. Currently, the City rents two trailer mounted diesel powered, vacuum assisted pumps and places them in position at the West College Storage Facility. The City plans to purchase two mobile pumps of similar capacity in lieu of renting and desires to construct permanent facilities to house and operate the pumps including a pad (with built-in containment), roof cover and connection to existing bypass piping. Additionally, a containment structure will be constructed for the disinfection chemicals at the West College Pump Station near the West College Recycled Water Pond.
11/04/2021Image
Construction
02396Local Sewer and Water Repairs On-Call Phase 18The purpose of this project is to have a structure in place to complete water and/or sewer system repairs or needed upgrades in a timely manner that come to the City's attention and are not scoped to be addressed on another project.
07/15/2021Image
Construction
00189Slater Street and Lewrosa Way Sewer and Water Main Replacement ProjectThis project will replace aged water main and sewer main in Lewrosa Way and in Slater Street from Lewis Road to Dexter Street. Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing older deteriorated VCP pipe reduces inflow and infiltration and reduces maintenance costs.The pavement will be reconstructed along Slater Street between Lewis Road and Dexter Street and in Lewrosa Way once mains have been replaced. Nine existing curb ramps will also be replaced.
07/15/2021Image
Completed
023762021 Pavement MarkingsThis project is for the annual contract maintenance installation of edge lines and bike lane lines throughout Santa Rosa. It is intended to ensure bicyclists remain within a bike pathway on the street system by highlighting travel lanes and bike lanes and to provide striping modifications to the street system as needed.

Santa Rosa City Hall - 100 Santa Rosa Avenue - Santa Rosa, CA 95404