Capital Improvement Project


Transit Mall Kiosk Alterations

Estimated Construction Schedule: Slated to begin September, 2026 and is anticipated to be completed May, 2027.
Construction Contract Amount: Pending
Project ID #: 2129
Description: Expansion and improvements to the Transit Mall Kiosk including a larger footprint, extend walls vertically to the ceiling, HVAC installation, customer counter improvements, and improved security.

Construction starts in September: The City Council awarded a construction contract to GCCI, Inc. of Santa Rosa, CA at the August 18 City Council meeting. The City and GCCI, Inc. are preparing to start construction in September. Beginning September 11, the Transit Mall Kiosk will be closed during construction and the service will be temporarily relocated to City Hall Annex at 90 Santa Rosa Ave until construction is completed.

Contacts:

Camron Macdonald
Project Manager
City of Santa Rosa
(707)543-3769
CMacDonald@srcity.org

Correspondence:
Invitation for Bids - FOR REFERENCE ONLY - see PlanetBids for Bidding information
Advance Construction Notice
Bid Tabs
Click for larger image
Project Image

Note: All dates and times are subject to change.