Estimated Construction Schedule: Slated to begin June, 2022 and is anticipated to be completed June, 2023.
Construction Contract Amount: $6,009,025
Project ID #: 2300
Description: This project will remove and replace fire damaged irrigation components within City right of way in the Coffey Park and Fountaingrove neighborhoods.

Construction Update Image

July 2022: This project was awarded to the lowest responsive bidder Bortolussi & Watkins Inc. on 3/15/2022. Construction management and inspection will be performed by Green Valley Consultant Engineering. Construction is slated to begin on 8/1/2022 with estimated completion in one year. Although the majority impacted area of work are outside of the roadway, temporary traffic impact will be expected to allow construction vehicle access whenever applicable. Please check back for future updates.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

Jason Balatti
Construction Manager
Green Valley Consulting Engineers
(707)579-0388
JasonB@Gvalley.com

Grant Bailey
Supervising Engineer
City of Santa Rosa
(707)543-4281
Gbailey@srcity.org

Other Information:
C02300 Invitation for Bids (for information only - see PlanetBids for bidding)
C01178 Plans
Bid Tabs