Fountaingrove Pkwy Water Main Upsize for High Fire Severity Zone

Estimated Construction Schedule: Slated to begin November, 2016 and is anticipated to be completed February, 2017.
Construction Contract Amount: $252,100
Project ID #: 1631
Description: The purpose of this project is to replace a section of a water main with a larger diameter pipe, located on Fountaingrove Parkway east of Fir Ridge Drive, in order to increase the water flow to existing reservoirs in a High Fire Severity Zone

Construction Update Image

Current Activity {For the month of March 2017}: Installation and acceptance of the new water main has been completed. Minor punch list work remaining. Temporary traffic control may be used during minor punch list work but traffic delays are not anticipated.

Contacts:

Christopher Catbagan
Associate Civil Engineer
City of Santa Rosa
(707)543-4521
ccatbagan@srcity.org

Chad Anderson
Quality Control Associate
City of Santa Rosa

CAnderson@srcity.org

Correspondence:
C01631 Invitation for Bids
C01631 Plans
C01631 Bid Tab
Construction Notice
Click for larger image
Project Image

Note: All dates and times are subject to change.