Fulton Rd Sidewalk Improvements - College Ave to Santa Rosa Creek Trail

Estimated Construction Schedule: Slated to begin December, 2017 and is anticipated to be completed February, 2018.
Construction Contract Amount: $178,356
Project ID #: 1817
Description: This project will provide sidewalk along the west side of Fulton Road from College Avenue to the existing driveway for the Santa Rosa Creek Trail.

Construction Update Image

CURRENT STATUS: Update 3/23/18 - Work is complete on Fulton Rd. Please “Tell us how we did” by following to the survey below.

Contacts:

Lisa Welsh
Associate Civil Engineer
City of Santa Rosa
(707)543-3909
LWelsh@srcity.org

Dave Stolte
Quality Control Associate
City of Santa Rosa

DStolte@srcity.org

Yukon Construction
Phone: (707) 576-7292

Correspondence:
Advance Project Notice
Advance Project Notice - Spanish
Imminent Project Notice
Imminent Project Notice - Spanish

Other Information:
C01817 Invitation for Bids (for information only - see PlanetBids for bidding)
C01817 Plans
C01817 Bid Results


Tell Us How We Did Image

Click for larger image
Project Image

Note: All dates and times are subject to change.