Fulton Rd Sidewalk Improvements - College Ave to Santa Rosa Creek Trail
Estimated Construction Schedule: Slated to begin December, 2017 and is anticipated to be completed February, 2018. Construction Contract Amount: $178,356 Project ID #: 1817 |
Description:
This project will provide sidewalk along the west side of Fulton Road from College Avenue to the existing driveway for the Santa Rosa Creek Trail.
|
|
Contacts: Lisa Welsh Associate Civil Engineer City of Santa Rosa (707)543-3909 LWelsh@srcity.org Dave Stolte Quality Control Associate City of Santa Rosa DStolte@srcity.org Yukon Construction Phone: (707) 576-7292 Correspondence: Advance Project Notice Advance Project Notice - Spanish Imminent Project Notice Imminent Project Notice - Spanish Other Information: C01817 Invitation for Bids (for information only - see PlanetBids for bidding) C01817 Plans C01817 Bid Results |
Click for larger image |