SMART Bus Turnout - Guerneville Road
Estimated Construction Schedule: Schedule for this project is not set. Construction Contract Amount: $107,590 Project ID #: 1964 |
Description:
This project will construct a bus turnout on Guerneville between the SMART rail and Herbert Lane. This is to be constructed prior to the implementation of rail passenger service and will accommodate the potential for up to 2 buses to stage in the turnout. The project will consist of an approximately 150 foot long turnout, the reconstruction of curb, gutter, and sidewalk, the relocation of a streetlight, power pole, tree removal and the installation of bus shelters. The bike lane will remain in its current alignment. Right of way has been acquired for this project.
|
|
Contacts: Gregory Dwyer Associate Civil Engineer City of Santa Rosa (707)543-3838 GDwyer@srcity.org Greg Loraditch Civil Engineering Tech III City of Santa Rosa GLoraditch@srcity.org Other Information: Addendum 1 Invitation For Bids Plans Bid Tabs |