City of Santa Rosa image CIP

Capital Improvement Project


Cobblestone Dr Zone R2-R4 Water Main Connection

Estimated Construction Schedule: Slated to begin April, 2023 and is anticipated to be completed October, 2024.
Construction Contract Amount: Pending
Project ID #: 1999
Description: The Project will install approximately 1,045 linear feet of new 10-inch diameter water main and a pressure-reducing assembly that will connect a high-pressure zone with a lower-pressure zone to improve fire protection in the Cobblestone neighborhood. Approximately 174 linear feet of 8-inch diameter water main will be added near the southern end of Cobblestone Drive to provide operational flexibility including the ability to isolate the Cobblestone neighborhood into a separate pressure zone.

Construction Update Image

October 2024: The project was accepted by the City and the NOC filed 10-18-24

Contacts:

Andrew Wilt
Associate Civil Engineer
City of Santa Rosa
(707)543-3878
awilt@srcity.org

Timothy Selle
Civil Engineering Tech II
City of Santa Rosa
+1 (707) 791-6147
TSelle@srcity.org

Ben Bryant
Consultant Design Engineer
Brelje and Race
707-576-1322
bryant@brce.com

Mike Janet
Consultant Construction Manager
Coastland
707-494-6464
janet@coastlandcivil.com

TEAM GHILOTTI INC.
Phone: (707) 763-8700
Fax: (707) 763-8711

Joe Moreira
Project Manager
TEAM GHILOTTI INC.
(707)953-9613
joem@teamghilotti.com

Fernando Romo
Foreman
TEAM GHILOTTI INC.
(415)328-0664

Correspondence:
Notice of Intent to Adopt a Mitigated Negative Declaration
Bid Tabs C01999

Other Information:
Final Initial Study – MND with Addendum April 2020
C01999 Invitation for Bids (for information only - see PlanetBids for bidding)
C01999 Plans (for information only - see PlanetBids for bidding)
Click for larger image
Project Image

Note: All dates and times are subject to change.