City of Santa Rosa image CIP

Capital Improvement Project


Cleveland Ave & St Rose District Sewer & Water Improvements

Estimated Construction Schedule: Slated to begin July, 2022 and is anticipated to be completed April, 2024.
Construction Contract Amount: $1,772,965
Project ID #: 2041
Description: This project will abandon approximately 700 feet of clay sewer main on the west side of Cleveland between Ridgway Avenue and Carrillo Street by transferring 23 laterals to an existing PVC sewer trunk on the east side of Cleveland Avenue. Additionally, this project will include sewer system improvements for 7th Street and B Street. The work on 7th Street will abandon 540 feet of clay sewer main and transfer 2 laterals to an existing sewer trunk between A Street and B Street. The work on B Street includes replacing a 30-foot section of deteriorated pipe near Healdsburg Avenue. This work will reduce inflow and infiltration and reduce maintenance costs.

Construction Update Image

Current Activity: 1/25/2024 All that remains for this project is street paving, pending weather conditions. Thank you for your patience.

Contacts:

Sara Mathews
Associate Civil Engineer
City of Santa Rosa
(707)543-3866
SMathews@srcity.org

Chris Huffman
Quality Control Associate
City of Santa Rosa
+1 (707) 696-9106
CHuffman@srcity.org

Clark Stauffer
Construction Manager
Coastland Civil
7076367010
stauffer@coastlandcivil.com

Bob Elze
Construction Inspector
Coastland Civil
7074813802
elze@coastlandcivil.com

Correspondence:
Advance Project Notice-Spanish
C02041 Invitation for Bids (for information only-see PlanetBids for bidding)
C02041 Plans (for information only-see PlanetBids for bidding)
Bid Tabs C02041
Imminent Construction Notice-English
Imminent Construction Notice-Spanish
Click for larger image
Project Image

Note: All dates and times are subject to change.