City of Santa Rosa image CIP

Capital Improvement Project


Farmers Lane Well Facility Pump Replacement Project

Estimated Construction Schedule: Slated to begin October, 2017 and is anticipated to be completed May, 2018.
Construction Contract Amount: $217,986
Project ID #: 2079
Description: In order to meet the proposed construction schedule for the Farmers Lane Well Rehabilitation Project, the well pumps will need to be pre-purchased due to the long lead time. A submersible pump is planned to be installed in W4-1 with a nominal pumping capacity of about 840 gpm. A vertical turbine pump is planned to be installed in W4-2 with a nominal capacity of about 1,660 gpm, providing a total capacity of 2,500 gpm.

Construction Update Image

Construction update - July 2, 2018: Bartley Pump started the installation of the pump at Well 4-2 on Thursday and Friday, June 28-29, 2018 as part of the Farmers Lane Well Rehabilitation Project (C01839 and C02079). They will finish the installation on Thursday July 5, 2018. No impacts to traffic on Farmers Lane are expected during the pump installation.

Contacts:

Jillian Tilles
Associate Civil Engineer
City of Santa Rosa
(707)543-3878
jtilles@srcity.org

Other Information:
C02079 IFB
C02079 Plans
C02079 Bid Tab
Click for larger image
Project Image

Note: All dates and times are subject to change.