City of Santa Rosa image CIP

Capital Improvement Project


Laguna Treatment Plant Filter Cells 9-14 Valve and Actuator Replacement

Estimated Construction Schedule: Slated to begin September, 2024 and is anticipated to be completed November, 2024.
Construction Contract Amount: Pending
Project ID #: 2096
Description: This project will address ongoing infrastructure replacement needs plant wide. This particular project will complete the procurement and installation of the remaining actuators and refurbish valves that control backwash for tiertiary filtration.
Contacts:

Chris Balanesi
Associate Civil Engineer
City of Santa Rosa
(707)543-3914
cbalanesi@srcity.org

Correspondence:
C02096 Invitation for Bids (for information only-see PlanetBids for bidding)
C02096 PLA Community Workforce Agreement (for information only - see PlanetBids for bidding)

Other Information:
C02096 Bid Tabs
Click for larger image
Project Image