Estimated Construction Schedule: Slated to begin July, 2017 and is anticipated to be completed August, 2017.
Construction Contract Amount: $354,125
Project ID #: 2099
Description: The purpose of this slurry seal project is to restore the pavement's ability to prevent water intrusion, correct minor cracking and improve skid resistance. This procedure includes covering (primarily residential) city streets with a thin, quarter-inch roadway coating of liquid asphalt and sand. Priorities for street selections are established by the Pavement Management System.

Construction Update Image

Current Project Status: Construction of this project is complete.

Contacts:

Grant Bailey
Assistant Engineer
City of Santa Rosa
(707)543-4508
gbailey@srcity.org

Ed Skultety
Civil Engineering Technician III
City of Santa Rosa
(707) 543-3877
eskultety@srcity.org

Correspondence:
Advance Project Notice for Area 1 - 3/15/2017
Advance Project Notice for Area 1 - Spanish - 3/15/2017
Advance Project Notice for Area 2 - 3/15/2017
Advance Project Notice for Area 2 - Spanish - 3/15/2017
Advance Project Notice for Area 3 - 3/15/2017
Advance Project Notice for Area 3 - Spanish - 3/15/2017
Project Schedule
Imminent Construction Notice for Area 2 - Spanish - 6/22/2017
Imminent Construction Notice for Area 1 - 6/22/2017
Imminent Construction Notice for Area 1 - Spanish - 6/22/2017
Imminent Construction Notice for Area 2 - 6/22/2017
Imminent Construction Notice for Area 3 - 6/22/2017
Imminent Construction Notice for Area 3 - Spanish - 6/22/2017

Other Information:
CORRECTED Invitation for Bids
C02099 Bid Tab


Measure M Image


Tell Us How We Did Image

Click for larger image
Project Image

Note: All dates and times are subject to change.