City of Santa Rosa image CIP

Capital Improvement Project


Geysers - Delta Connection Improvement

Estimated Construction Schedule: Slated to begin August, 2021 and is anticipated to be completed October, 2021.
Construction Contract Amount: Pending
Project ID #: 2111
Description: Upsize the connection between Delta Pond and the existing 33" Geysers Line which ends just outside the toe of the pond. The length need to be upsized is approximately 130 feet from 12" to approximately 24" to 33". Upsizing this connection will allow recycled water to be delivered to Delta Pond using the Geysers pipeline in the event that the aged reclamation piping network is compromised and will provide redundancy.
Contacts:

Andrew Wilt
Associate Civil Engineer
City of Santa Rosa
(707)543-3878
awilt@srcity.org

Cy Penry
Civil Engineering Tech III
City of Santa Rosa
+1 (707) 529-9210
CPenry@srcity.org

David Coleman
Consultant Design Engineer
Brelje and Race
707) 636-3756
coleman@brce.com
Click for larger image
Project Image

Note: All dates and times are subject to change.