Capital Improvement Project


Oakmont Dr. Sewer Main Upsizing Oakmont Creek to Greenfield Cir

Estimated Construction Schedule: Slated to begin April, 2019 and is anticipated to be completed September, 2019.
Construction Contract Amount: Pending
Project ID #: 2137
Description: Replace approximately 1188 feet of 6 inch ACP main with 10 inch PVC in Oakmont Drive (Oakmont Creek to Greenfield Circle) as this section is undersized and has resulted in two sanitary sewer overflows since 2009. Pedestrian ramps will be upgraded to current standards within the project limits.
Contacts:

Gregory Dwyer
Associate Civil Engineer
City of Santa Rosa
(707)543-3838
GDwyer@srcity.org

Other Information:
Advance Notice Letter
Invitation for Bids *Not for Bidding Purposes*
Plans *Not for Bidding Purposes*
Bid Tab
Click for larger image
Project Image

Note: All dates and times are subject to change.