City of Santa Rosa image CIP

Capital Improvement Project


MSCN Stockpile Pad Replacement

Estimated Construction Schedule: Slated to begin August, 2019 and is anticipated to be completed October, 2019.
Construction Contract Amount: $186,500
Project ID #: 2182
Description: The Project will replace 6,600 square feet of existing asphalt surface with portland cement concrete paving in the MSCN Corporation Yard. The proposed replacement of a rectangular shaped pavement area fronts the existing stockpile bays where construction aggregate material is stored. This project will give City Maintenance Crews an improved durable pavement surface to work from and allow the loose aggregate materials, originating from material stockpiles, to be swept up and collected prior to any rain storm events. Construction is expected to start August 2019, and will last for approximately a month.

Construction Update Image

Current Activity for October 2019: Work is underway on this project and is expected to be completed by the end of October 2019.

Contacts:

Christopher Catbagan
Associate Civil Engineer
City of Santa Rosa
(707)543-4521
ccatbagan@srcity.org

Chad Anderson
Quality Control Associate
City of Santa Rosa

CAnderson@srcity.org

Correspondence:
Invitation for Bids **Not for Bidding Purposes, MUST USE PLANETBIDS FOR BIDDING**
C02182_BidTabs

Other Information:
Plans *Not for Bidding Purposes, MUST USE PLANETBIDS FOR BIDDING*
Click for larger image
Project Image

Note: All dates and times are subject to change.