|
Fire Station 5 Resiliency and Relocation
Estimated Construction Schedule: Slated to begin November, 2023 and is anticipated to be completed June, 2026. Construction Contract Amount: Pending Project ID #: 2184 |
|
Description:
This project will rebuild a permanent Fire Station at a new location that will improve response times for the service area, provide space for a larger facility that will support upstaffing during significant weather events and to serve as a forward command post during large emergencies. For more information: srcity.org/FireStation5
Punch list in progress: The project is generally complete, with the Fire Department moved in and all public right of way areas are open. Some punch list items are expected to take several months to complete due to long lead times; however, should be little to no public impacts. |
|
|
Contacts: Camron Macdonald Project Manager City of Santa Rosa (707)543-3769 CMacDonald@srcity.org Stephen McCulloch Design-Builder Project Manager Wright Contracting 707.528.1172 SMcCulloch@wrightcontracting.com Correspondence: Cultural Resource Letter Cultural Resource Letter - Spanish DBIA Presentation (public reference only) Other Information: Notice of Intent Notice of Intent - Spanish 2184 FS5 FONSI Public Notice 2184 FS5 FONSI Public Notice- Spanish 2184 NEPA_NOI-RROF_eng 2184 NEPA_NOI-RROF_esp 2005-0137 Traffic Signal Record Plans 2184 FS5 EA 2184 FS5 ISMND 12-10-21 2184 FS5 MMRP 12-1-21Final 2184 FS5 Prelim Design Plans Photos: Proposed location of new fire station |
Click for larger image
|