Capital Improvement Project


Bicycle and Pedestrian Gap Closures - Piner Rd and Dutton Ave

Estimated Construction Schedule: Slated to begin December, 2019 and is anticipated to be completed June, 2020.
Construction Contract Amount: $1,158,961
Project ID #: 2198
Description: The project has two locations. The first location will rehabilitate the outside lanes of pavement and provide bicycle lanes on Piner Road between Coffey Lane and Range Avenue. The second location will provide a sidewalk on the east side of Dutton Avenue just south of Jennings Avenue. Both locations will include upgrading the curb ramps to current standards.

Construction Update Image

June 2020: Construction on schedule to be completed by July 2020.

Contacts:

Lisa Welsh
Associate Civil Engineer
City of Santa Rosa
(707)543-3909
LWelsh@srcity.org

Adam Felix
Construction Inspector
Coastland
(707) 806-9276
felix@coastlandcivil.com

Mike Janet
Construction Manager
Coastland
(707) 494-6464
janet@coastlandcivil.com

Correspondence:
Advance Construction Notice
Advance Construction Notice - Spanish
Imminent Construction Notice
Imminent Construction Notice - Spanish

Other Information:
C02198 Invitation for Bids (for information only - See PlanetBids for bidding)
C02198 Plans
C02198 Bid Results


Tell Us How We Did Image

Click for larger image
Project Image

Note: All dates and times are subject to change.