Skyfarm A and Hansford Court Lift Station Reconstruction

Estimated Construction Schedule: Slated to begin August, 2020 and is anticipated to be completed July, 2021.
Construction Contract Amount: $3,388,000
Project ID #: 2201
Description: Two lift stations were severely damage during the Tubbs Fire. One is located on SkyFarm Drive near Saint Andrews Drive and the other at the end of Hansford Court. They both must be reconstructed.

Construction Update Image

Current Activity - July 2021: Pacific Infrastructure Corporation is on site daily at Skyfarm A and Hansford Court sewer lift stations. Skyfarm - Building pad has been placed and anticipating CMU Block to begin installation August 2, 2021. Hansford Court is further along on construction. Replacement standby genertor, pumps and equipment have been tested but awaiting the BAAQMD permit to operate and anticipate the Permit August, 2021 switch over the site to the new equipment and allow the remaining work to remove the old equipment, place asphalt surfacing and fencing.

Contacts:

Eric Frye
Quality Control Associate
City of Santa Rosa
(707)543-3858
EFrye@srcity.org

Correspondence:
C02201 Invitation for Bids (for information only-see PlanetBids for bidding)
C02201 Plans (for information only-see PlanetBids for bidding)
Bid Tab
C02201_Bid Tabs Updated
Imminent Construction Notice-English
Imminent Construction Notice-Spanish
Location Map
Click for larger image
Project Image

Note: All dates and times are subject to change.