City of Santa Rosa image CIP

Capital Improvement Project


Skyfarm A and Hansford Lift Stations Reconstructions-Fire Related

Estimated Construction Schedule: Slated to begin April, 2019 and is anticipated to be completed October, 2019.
Construction Contract Amount: Pending
Project ID #: 2201
Description: Two lift stations were severely damage during the Tubbs Fire. One is located on SkyFarm Drive near Saint Andrews Drive and the other at the end of Hansford Court. They both must be reconstructed.

Additional News for September 2018: The engineering consulting firm Hazen & Sawyer from San Jose, CA, has been retained to evaluate the fire related damage and to prepare plans to repair the sewer lift stations.

Contacts:

Mark Kasraie
Associate Civil Engineer
City of Santa Rosa
(707)543-3857
MKasraie@srcity.org
Click for larger image
Project Image