City of Santa Rosa image CIP

Capital Improvement Project


Fire Damaged Street Lights Replacement In Coffey Park

Estimated Construction Schedule: Slated to begin January, 2020 and is anticipated to be completed June, 2020.
Construction Contract Amount: Pending
Project ID #: 2233
Description: This project will replace 229 fire damaged street lights in the Coffey Park area.

Current Status (August 2019): This project advertises for bids starting October 3, 2019, with bid opening on November 7, 2019.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

Correspondence:
Bid Tabs

Other Information:
C02233 Invitation for Bids (for information ony - see PlanetBids for bidding)
C02233 Plans
Click for larger image
Project Image

Note: All dates and times are subject to change.