Fire Damaged Street Lights Replacement In Coffey Park

Estimated Construction Schedule: Slated to begin May, 2020 and is anticipated to be completed October, 2020.
Construction Contract Amount: $1,791,513
Project ID #: 2233
Description: This project will replace 229 fire damaged street lights in the Coffey Park area.

Construction Update Image

November 2020: Majority of work completed. Punch list items remain.

Contacts:

Danny Chen
Assistant Engineer
City of Santa Rosa
(707)543-3911
DChen@srcity.org

Todd Amador
ST. FRANCIS ELECTRIC
(510)750-7461

Correspondence:
Imminent Construction Notice
Imminent Construction Notice - Spanish

Other Information:
C02233 Invitation for Bids (for information ony - see PlanetBids for bidding)
C02233 Plans
Bid Tabs
Click for larger image
Project Image