La Paloma Ave / East Haven Dr / Rogers Wy Sewer and Water Main Replacement
Estimated Construction Schedule: Slated to begin June, 2020 and is anticipated to be completed November, 2020. Construction Contract Amount: Pending Project ID #: 308 |
Description: This project is one phase of the replacement of Grace neighborhood water and sewer mains. Sewer and water mains replacements planned for this phase of work include: East Haven Dr from 4th St to Eleanor, La Paloma Ave from East Haven Dr to Rogers Way, and Rogers Way from La Paloma Ave to 4th St. Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing sewer main pipe reduces inflow and infiltration and also reduces maintenance costs. All streets will be reconstructed and minor stormdrain and pedestrian ramp improvements will be made at the intersection of East Haven Dr and La Paloma Ave. | |
Contacts: Grant Bailey Associate Civil Engineer City of Santa Rosa (707)543-4508 gbailey@srcity.org Correspondence: Advance Project Notice Advance Project Notice-Spanish Other Information: Bid Tabulation C00308 Invitation for Bids (for information only - see PlanetBids for bidding) C00308 Plans (for information only) |
Click for larger image |