Cleveland Ave & St Rose District Sewer & Water Improvements
Estimated Construction Schedule: Slated to begin May, 2022 and is anticipated to be completed January, 2023. Construction Contract Amount: Pending Project ID #: 2041 |
Description: This project will abandon approximately 700 feet of clay sewer main on the west side of Cleveland between Ridgway Avenue and Carrillo Street by transferring 23 laterals to an existing PVC sewer trunk on the east side of Cleveland Avenue. Additionally, this project will include sewer system improvements for 7th Street and B Street. The work on 7th Street will abandon 540 feet of clay sewer main and transfer 2 laterals to an existing sewer trunk between A Street and B Street. The work on B Street includes replacing a 30-foot section of deteriorated pipe near Healdsburg Avenue. This work will reduce inflow and infiltration and reduce maintenance costs. | |
Contacts: Jason Roberts Supervising Engineer City of Santa Rosa (707)543-3857 JRoberts@srcity.org Correspondence: Advance Project Notice-Spanish C02041 Invitation for Bids (for information only-see PlanetBids for bidding) C02041 Plans (for information only-see PlanetBids for bidding) Bid Tabs C02041 Imminent Construction Notice-English Imminent Construction Notice-Spanish |
Click for larger image![]() |